Guide · Approvals

Building control inspections: what gets checked and when

Building control inspections are the site visits that check your work against the Building Regulations as it is built. On an extension they typically cover the foundations, damp-proofing, drains, structure and insulation, then completion. Whoever carries out the work must notify the inspector before it starts and before covered work is hidden.

Extension under construction with the floor slab, blockwork and a steel beam ready for inspection (illustrative)
Ready for a building control visit · illustrative Fig. 01

Owners tend to picture building control as a single sign-off at the end. In practice it is a series of visits during the build, and the sequence matters. If a stage is covered before it has been seen, the regulations allow the authority to have it opened up again. Knowing which stages are inspected, and who has to call the inspector, keeps the job moving and keeps the completion certificate on track.

This guide covers who inspects and which stages are checked on an extension or loft conversion. It explains what notice the regulations require, who arranges the visits on a managed project, what happens when something fails, and how the completion certificate is issued. It sits within the approvals framework, which explains how building control relates to planning permission and the Party Wall Act.

Who carries out building control inspections?

Two kinds of body can inspect. The local authority's building control service covers every address in its area. A private registered building control approver can be used instead; the approver tells the council about the work by serving an initial notice[5]. Approvers were previously called approved inspectors. Under the Building Safety Act changes, the new registration system became mandatory from 6 April 2024, with registration lasting five years[4].

Whichever body you use, its job is to check that the work complies with the Building Regulations. Officers will normally visit at various stages. They will not be present for the great majority of the project, and they do not act as a site manager or clerk of works[6]. That distinction matters when you read the completion certificate later: it confirms compliance based on the inspections made, not the quality of every finish.

Which stages are inspected on an extension or loft conversion?

The regulations no longer list a fixed set of stage notices for England. Since October 2023 they fix the start and completion notices and leave the stages between to the building control body[3]. In practice the stages are consistent across bodies, because they follow the order in which work gets covered up. The Planning Portal lists the excavation for a foundation, the foundation itself, any damp-proof course and any concrete laid over the site, each before it is covered[1]. LABC's guidance for extensions adds the commencement visit, the drains, the roof structure and completion[2].

Typical inspection stages on a house extension

Stage What the inspector checks What has to wait
Commencement That the work matches the approved drawings and the site is set up as described[2] Nothing is covered yet
Foundation excavations Ground bearing capacity, depth, nearby drains and manholes, trees and roots, contamination[2] Concrete is not poured until the trench has been seen
Foundation concrete Depth and placing of the concrete against the design[1] Walls are not built off it until seen
Oversite and damp-proof course Hardcore and blinding, the damp-proof membrane and its gauge, floor insulation and concrete thickness, the damp-proof course level[2] The floor is not cast and the DPC not covered until seen
Drains Pipe runs, bedding and falls before backfilling, then a test after backfill[2] Trenches stay open until seen
Structure Steel beams and bearings, floor joists and the roof structure against the engineer's design; roof pitch, insulation and ventilation[2] Beams are not boxed in until seen
Pre-plaster Wall and roof insulation, fire protection, cavity barriers, and on a loft the escape route, stairs and fire doors Plasterboard goes on after the visit
Completion The finished work, before the completion certificate is issued[2]; drains tested for air and water tightness once the work is complete[2] The completion notice is given within five days of finishing[3]

Scroll sideways to see all columns

A loft conversion follows the same pattern without the groundwork. The structural visit checks the new floor joists and the steels bearing on the party walls. The pre-plaster visit checks the escape route from the new room: the staircase, the fire doors along it and the protected landing. Insulation in the roof slope and at the dormer is checked before it is lined. Some elements are certified by the installer instead, through a competent person scheme. Replacement windows and a new consumer unit are the usual examples. The inspector is not called for those.

What notice do you have to give, and when?

For England, regulation 16 of the Building Regulations 2010 requires two notices. One goes in before work starts, so that at least two days have elapsed since the end of the day on which it was given. The other goes in not more than five days after the work has been completed. If a building is to be occupied before completion, at least five days' notice of that is needed too[3]. Miss a notice and the authority can require you to cut into, lay open or pull down as much of the work as prevents it from checking compliance[3].

Two further rules came in with the Building Safety Act changes. A notice must be given no more than five working days after the work has satisfied the new definition of commencement. For a house extension, that point is reached when the sub-surface structure is complete: all foundations, any basement and the structure of the ground floor. For other building work, it is when 15 per cent of the proposed work is done. And building control approval lapses automatically after three years if the work has not commenced[4]. For the stages in between, the Planning Portal describes the notice required as at least one whole day in practice. The work pauses to give the authority time to inspect[1].

Who arranges the inspections on a project?

The regulations place the duty on the person carrying out the work, which on a contracted job is the builder. The application itself may be made by the owner, the designer or the builder, depending on who prepared the Building Regulations drawings. On a managed project the sequence is simple. The builder books each inspection as the work reaches that stage, holds the next operation until the visit has happened, and records the outcome. The owner remains responsible for the work complying, so it is worth asking at the start who is booking what.

On an E&N Build Group job the building control application can be made by you or arranged through us, as our project working arrangements explain, and the certificates and sign-offs for the work done are handed over at the end. Agree in the written scope who gives the notices and books each inspection. If you have appointed a designer, ask for them to be copied in on any query the inspector raises about the design.

What happens at a visit, and what if something fails?

The inspector compares what is on site with the approved drawings and the structural engineer's calculations. Where the drawings are silent, the regulations themselves are the test. On a foundation visit that means looking in the trench. On a structural visit it means checking the beam sizes, bearings and connections against the engineer's design. Visits are short; the preparation is in having the right documents on site.

If something falls short, the inspector says so and the work is put right and seen again before it is covered. Two causes are common on extensions. Foundations that need to go deeper than the drawings assumed, because of ground conditions or tree roots. And drainage runs that differ from the plan once the ground is opened. Neither is unusual. What creates problems is covering the work first and asking afterwards, because the authority can then require it to be exposed[3].

The completion certificate, and what it does not cover

When the work is finished, the completion notice is given within five days and the body carries out its final inspection. GOV.UK says you will usually get a completion certificate within eight weeks of completion of the building work, as long as it complies[5]. The certificate is issued to the owner and should be kept with the house's documents, alongside the installer certificates for windows, electrics and heating; solicitors ask for all of them on a sale.

A certificate is not a guarantee that all works have been done to the required standard[6]. Building control checks compliance with the regulations at the stages it sees; it does not supervise the work generally or pass judgement on finishes. The paint, the tiling and the way the doors close are matters between you and your builder, which is why snagging after the completion certificate is a separate step with its own list. For work done in the past without approval, the local authority can consider a regularisation certificate; only work carried out after 11 November 1985 can be approved that way[5].

FAQ

Questions people ask during the build.

How much notice does building control need for an inspection?

The regulations fix two notices: at least two days before work starts, and no more than five days after it is completed. For the stages in between, the Planning Portal describes the notice required as at least one whole day in practice, and work at those stages should pause until the inspection has happened. Ask your building control body how it prefers to be booked; many take requests online or by phone for the next working day.

Do I need to be at home for a building control inspection?

No. The inspector needs access to the work, not to you, and on most projects the builder meets them. It helps if the approved drawings and the structural engineer's calculations are on site. If you want to hear the inspector's view first hand, ask the builder when the visit is booked; completion inspections in particular are worth attending.

What happens if the inspector is not satisfied?

The work is corrected and inspected again before it is covered. The inspector will say what falls short of the regulations, usually with reference to the approved drawings or the engineer's design. If work has already been covered without a visit, the regulations allow the authority to require it to be opened up so that it can be checked. Nothing is signed off until it complies.

Is building control the same as planning permission?

No. Planning permission is about what you build and whether it is acceptable in its setting. Building control checks how it is built against the Building Regulations: structure, fire safety, insulation, ventilation, drainage and so on. A job can need both, or only one. The approvals framework guide sets out which applies to which kind of work.

Can I use a private inspector instead of the council?

Yes. You can choose the local authority's building control service or a private registered building control approver, who tells the council about the work by serving an initial notice. Since 6 April 2024 private approvers have had to be registered with the Building Safety Regulator. Either route ends in a completion certificate; only the local authority can issue a regularisation certificate for work done without approval.

How long does the completion certificate take?

GOV.UK says you will usually get a completion certificate within eight weeks of the building work being completed, as long as it complies. The clock starts when the building control body receives notice that the work is finished, which must be given within five days of completion. Keep the certificate with the house's papers: buyers and their solicitors will ask for it.

Does the completion certificate guarantee the work?

No. The Ombudsman's fact sheet is clear that a certificate is not a guarantee that all works have been done to the required standard. Inspections are visits at stages, not supervision, and building control does not act as a site manager or clerk of works. Quality and finish are matters for your contract with the builder, which is why snagging is a separate step.

Sources

Where the rules above come from.

Official sources checked on 1 October 2026. Fees and permitted development limits change; the dates show when each was read.

  1. Planning Portal,
    Building control: site inspections
    (accessed 1 Oct 2026)
  2. LABC Front Door,
    What building control site inspections should I expect for my new extension?
    (accessed 1 Oct 2026)
  3. legislation.gov.uk,
    The Building Regulations 2010, regulation 16 (notices)
    (accessed 1 Oct 2026)
  4. GOV.UK (DLUHC),
    Building circular letter: changes to the building control process, January 2024 update
    (accessed 1 Oct 2026)
  5. GOV.UK,
    Building regulations approval: how to apply
    (accessed 1 Oct 2026)
  6. Local Government and Social Care Ombudsman,
    Fact sheet: building control (April 2025)
    (accessed 1 Oct 2026)