Owners tend to picture building control as a single sign-off at the end. In practice it is a series of visits during the build, and the sequence matters. If a stage is covered before it has been seen, the regulations allow the authority to have it opened up again. Knowing which stages are inspected, and who has to call the inspector, keeps the job moving and keeps the completion certificate on track.
This guide covers who inspects and which stages are checked on an extension or loft conversion. It explains what notice the regulations require, who arranges the visits on a managed project, what happens when something fails, and how the completion certificate is issued. It sits within the approvals framework, which explains how building control relates to planning permission and the Party Wall Act.
Who carries out building control inspections?
Two kinds of body can inspect. The local authority's building control service covers every address in its area. A private registered building control approver can be used instead; the approver tells the council about the work by serving an initial notice[5]. Approvers were previously called approved inspectors. Under the Building Safety Act changes, the new registration system became mandatory from 6 April 2024, with registration lasting five years[4].
Whichever body you use, its job is to check that the work complies with the Building Regulations. Officers will normally visit at various stages. They will not be present for the great majority of the project, and they do not act as a site manager or clerk of works[6]. That distinction matters when you read the completion certificate later: it confirms compliance based on the inspections made, not the quality of every finish.
Which stages are inspected on an extension or loft conversion?
The regulations no longer list a fixed set of stage notices for England. Since October 2023 they fix the start and completion notices and leave the stages between to the building control body[3]. In practice the stages are consistent across bodies, because they follow the order in which work gets covered up. The Planning Portal lists the excavation for a foundation, the foundation itself, any damp-proof course and any concrete laid over the site, each before it is covered[1]. LABC's guidance for extensions adds the commencement visit, the drains, the roof structure and completion[2].
Typical inspection stages on a house extension
| Stage | What the inspector checks | What has to wait |
|---|---|---|
| Commencement | That the work matches the approved drawings and the site is set up as described[2] | Nothing is covered yet |
| Foundation excavations | Ground bearing capacity, depth, nearby drains and manholes, trees and roots, contamination[2] | Concrete is not poured until the trench has been seen |
| Foundation concrete | Depth and placing of the concrete against the design[1] | Walls are not built off it until seen |
| Oversite and damp-proof course | Hardcore and blinding, the damp-proof membrane and its gauge, floor insulation and concrete thickness, the damp-proof course level[2] | The floor is not cast and the DPC not covered until seen |
| Drains | Pipe runs, bedding and falls before backfilling, then a test after backfill[2] | Trenches stay open until seen |
| Structure | Steel beams and bearings, floor joists and the roof structure against the engineer's design; roof pitch, insulation and ventilation[2] | Beams are not boxed in until seen |
| Pre-plaster | Wall and roof insulation, fire protection, cavity barriers, and on a loft the escape route, stairs and fire doors | Plasterboard goes on after the visit |
| Completion | The finished work, before the completion certificate is issued[2]; drains tested for air and water tightness once the work is complete[2] | The completion notice is given within five days of finishing[3] |
Scroll sideways to see all columns
A loft conversion follows the same pattern without the groundwork. The structural visit checks the new floor joists and the steels bearing on the party walls. The pre-plaster visit checks the escape route from the new room: the staircase, the fire doors along it and the protected landing. Insulation in the roof slope and at the dormer is checked before it is lined. Some elements are certified by the installer instead, through a competent person scheme. Replacement windows and a new consumer unit are the usual examples. The inspector is not called for those.
What notice do you have to give, and when?
For England, regulation 16 of the Building Regulations 2010 requires two notices. One goes in before work starts, so that at least two days have elapsed since the end of the day on which it was given. The other goes in not more than five days after the work has been completed. If a building is to be occupied before completion, at least five days' notice of that is needed too[3]. Miss a notice and the authority can require you to cut into, lay open or pull down as much of the work as prevents it from checking compliance[3].
Two further rules came in with the Building Safety Act changes. A notice must be given no more than five working days after the work has satisfied the new definition of commencement. For a house extension, that point is reached when the sub-surface structure is complete: all foundations, any basement and the structure of the ground floor. For other building work, it is when 15 per cent of the proposed work is done. And building control approval lapses automatically after three years if the work has not commenced[4]. For the stages in between, the Planning Portal describes the notice required as at least one whole day in practice. The work pauses to give the authority time to inspect[1].
Who arranges the inspections on a project?
The regulations place the duty on the person carrying out the work, which on a contracted job is the builder. The application itself may be made by the owner, the designer or the builder, depending on who prepared the Building Regulations drawings. On a managed project the sequence is simple. The builder books each inspection as the work reaches that stage, holds the next operation until the visit has happened, and records the outcome. The owner remains responsible for the work complying, so it is worth asking at the start who is booking what.
On an E&N Build Group job the building control application can be made by you or arranged through us, as our project working arrangements explain, and the certificates and sign-offs for the work done are handed over at the end. Agree in the written scope who gives the notices and books each inspection. If you have appointed a designer, ask for them to be copied in on any query the inspector raises about the design.
What happens at a visit, and what if something fails?
The inspector compares what is on site with the approved drawings and the structural engineer's calculations. Where the drawings are silent, the regulations themselves are the test. On a foundation visit that means looking in the trench. On a structural visit it means checking the beam sizes, bearings and connections against the engineer's design. Visits are short; the preparation is in having the right documents on site.
If something falls short, the inspector says so and the work is put right and seen again before it is covered. Two causes are common on extensions. Foundations that need to go deeper than the drawings assumed, because of ground conditions or tree roots. And drainage runs that differ from the plan once the ground is opened. Neither is unusual. What creates problems is covering the work first and asking afterwards, because the authority can then require it to be exposed[3].
The completion certificate, and what it does not cover
When the work is finished, the completion notice is given within five days and the body carries out its final inspection. GOV.UK says you will usually get a completion certificate within eight weeks of completion of the building work, as long as it complies[5]. The certificate is issued to the owner and should be kept with the house's documents, alongside the installer certificates for windows, electrics and heating; solicitors ask for all of them on a sale.
A certificate is not a guarantee that all works have been done to the required standard[6]. Building control checks compliance with the regulations at the stages it sees; it does not supervise the work generally or pass judgement on finishes. The paint, the tiling and the way the doors close are matters between you and your builder, which is why snagging after the completion certificate is a separate step with its own list. For work done in the past without approval, the local authority can consider a regularisation certificate; only work carried out after 11 November 1985 can be approved that way[5].