What is written down at handover is what you rely on later. A snag found on the walk-round is a line on a list. A year later, the same fault is a defect, and the paperwork decides how easily it is put right. This guide covers the handover, the snagging list, later defects, your rights and where to go if a problem is not resolved. For the stages before handover, see how we work.
What should a building handover include?
Three things: a walk-round of the finished work, an agreed list of snags, and the documents. Snags are small faults or unfinished items, such as a door that catches. A defect is a fault in the work that may only show later. Hold the walk-round once the work is complete and the site is cleared.
Bring the written scope, the drawings and a note of any changes agreed during the build, because the scope is what the work is measured against. With E&N Build Group, the written scope comes with the quotation. It states what is included, what is not, and what was provisional until the work opened up.
If the work needed Building Regulations approval, GOV.UK says the completion certificate usually follows within eight weeks of completion, as long as the work complies[4]. It is not a guarantee that all the work meets the required standard, and building control officers do not act as site managers[5].
Which documents should the builder give you at completion?
It depends on the work. The table lists the common ones and when each applies.
Documents to collect at handover
| Document | What it shows | Who issues it | When it applies |
|---|---|---|---|
| Building Regulations completion certificate | The work complied with the Building Regulations, based on the inspections made[5] | Your building control body | Work that needed Building Regulations approval, such as an extension, a loft conversion or a structural alteration[4] |
| Competent person scheme certificate | A registered installer has certified the work as compliant; it is evidence of compliance and shows up in solicitors' searches[6] | The installer, through its scheme: for example FENSA or Certass for windows and doors, and Gas Safe Register for gas appliances[7] | Replacement windows and doors, a new boiler, and other work done by a scheme member instead of a building control application[6] |
| Electrical Installation Certificate or Minor Works Certificate | The electrical work meets BS 7671, the UK national standard for electrical safety[8] | The electrician who did the work | New wiring, circuits, sockets or lighting. A registered electrician also arranges a certificate that the work meets the Building Regulations[8] |
| Operating and maintenance instructions | How to run and look after heating and other fixed building services | The installer | Where a boiler or other fixed building service is installed or replaced |
| Manufacturers' guarantees and product manuals | Product cover and care instructions, for example for windows, flooring, kitchen units and appliances | The manufacturer, passed on with the product | Where the product comes with them; check whether any need registering in your name |
Scroll sideways to see all columns
Gas is a special case. By law, anyone doing work on gas appliances and fittings as part of their business must be competent and registered with Gas Safe Register[9].
At handover with E&N Build Group, you receive the certificates and sign-offs that apply to the work done. Some, such as the completion certificate, can arrive later, so note which are still to come. Keep them all with the drawings.
How to write and agree a snagging list
1. Walk round in daylight, room by room
Go round with the builder in daylight, with the scope and drawings, through every room the job touched. Open, close and switch everything a user would. Do not open up electrical fittings or touch gas appliances; faults there are for the installer.
2. Check the places snags usually appear
- Walls and ceilings. Cracks, paint runs, and making good around new sockets, pipes and frames.
- Doors and windows. Each one opens, closes and locks without force.
- Floors and tiling. Level edges, complete grout and sealant, fixed trims.
- Kitchens and bathrooms. Doors and drawers aligned, neat sealant, no drips under the sinks.
- Services. Every light, socket, tap and radiator works, and the consumer unit is labelled.
Outside. After render, roof work or an extension, check that vents, chimneys and flues are not removed, damaged, blocked or enclosed[9].
- Clearing up. Waste gone, and paths and gardens left as agreed.
3. Write each item so it cannot be misread
Number every item and give its location, what is wrong and what finished looks like. For example: kitchen, left of the window, plaster not made good around the new socket. Photograph each one; Citizens Advice suggests photos as evidence of a problem[3]. Anything the scope never included is a change, not a snag.
4. Agree the list, the dates and access
Agree the list in writing, by both signing it or by an email that attaches it. For each item, agree who does it, by when, and when they need access. If the contract links a final payment to completion, check how the snagging list affects it.
5. Check off each item and close the list
When each item is done, mark it closed with the date. Keep the closed list with the certificates. It shows what was fixed if a fault comes back.
How to raise a defect after handover
Some faults only show after a heating season or wet weather. Raise them like a snag, with photos. Citizens Advice advises complaining in writing where you can, and setting a date by which the work must be finished[3]. Send it to the contact named in your contract and keep a copy.
Some contracts include a defects period, also called a rectification period: a set time after completion when the builder agrees to return and put defects right. Its length and scope are whatever the contract says. It does not replace your statutory rights, and no contract term can exclude the duty of reasonable care and skill[1].
What are your rights after handover?
Under the Consumer Rights Act 2015, a trader must perform a service with reasonable care and skill[1], and that includes building work for a homeowner[3]. What the trader said or wrote about the service also counts as a term of the contract, if you took it into account when deciding[1].
If the work falls short, you can require the trader to do it again, which the Act calls repeat performance. The trader must do it within a reasonable time, without significant inconvenience to you, and bear the cost, including labour and materials[1]. If that is impossible or not done in a reasonable time, you can require a price reduction instead[1].
Court action has a time limit. An action founded on a simple contract cannot be brought more than six years after the cause of action accrued[2]. Raise problems promptly, and take legal advice on the dates if a claim may be needed.
If the problem is not resolved
Start with the complaints route in the contract. If that does not settle it, these are the next steps:
Trade association. If the trader belongs to one, contact it for advice[3].
Competent person scheme. Schemes have complaints procedures for problems with work their members did[6].
Citizens Advice. Its consumer service advises by phone or online chat, and it can report serious safety issues to Trading Standards[3].
Alternative dispute resolution. A way of settling a disagreement without going to court[3].
- Legal advice. A solicitor can advise on a claim, within the time limit above.
What you should have at the end
- A snagging list agreed in writing, with every item closed and dated.
- The certificates that apply to the work, or a note of those still to come.
- Instructions, manuals and guarantee paperwork, and a named contact for defects.
Planning your next project
The records from this job are where the next designer starts. If you are planning your next project, such as a new kitchen, the electrical certificates show what was installed. If you are considering adding a loft conversion later, the structural drawings and completion certificate show what was built and approved. Every listed service can be booked as a standalone job.