Most building projects change somewhere between the quotation and handover. You want a different layout, opening up a wall shows something no one could see, or the inspector asks for a different detail. That is normal. The trouble starts when a change is agreed in passing, priced later and recorded nowhere.
This guide covers changes after the work has been agreed, from raising one to settling a disagreement. It is general information, not legal advice on your contract. For the stages of a job from site visit to handover, see how building projects work with E&N Build Group.
Why do changes happen once work has started?
Changes come from four directions. Record the cause each time, because it is the first question asked about cost.
- Your choice. A different kitchen layout, extra sockets or a wider opening. The earlier you decide, the less is undone.
Hidden conditions. Some things only show once the work opens up: rotten joists, a drain in the wrong place, or what lies behind old plaster. Asbestos may be present in any building built or refurbished before 2000. If it is suspected, work should stop until it is identified, or assumed to be asbestos, and the risk is assessed[10].
- Gaps in the design. When the drawings do not show a detail, the builder needs an instruction and the designer may issue a revised drawing. That is a change, even if the price does not move.
Regulatory requirements. The work on site must comply with the Building Regulations, whatever the drawings show[4]. An inspector's request at a stage visit becomes a change too.
What you need before you ask for a change
A change is measured against what was agreed, so start with the original paperwork.
- The written scope and quotation. On an E&N Build Group job, you get a written scope with the quotation before work starts. It states what is included, what is not, and what is provisional because it cannot be known until the work opens up.
- The drawings, with revision numbers. A change is easier to describe against a numbered drawing.
- Any party wall notice or award. Both describe the notifiable work.
- Who decides. Agree who instructs changes on your side and who confirms them on the builder's.
A good quotation also says when the price can go up, for example only if you agree to extra work[6]. If you are not sure what the price covers, start with understanding the original quotation.
How to agree a change, step by step
1. Raise it in writing
An email is enough. Say what the change is, where and why, and attach a sketch, photo or marked-up drawing. A change agreed in conversation is easy to remember differently a month later.
2. Ask what it affects
Moving a doorway can move a light switch, a radiator and a floor finish. Ask the builder, and any designer or engineer, what else it touches: structure, services, other trades, materials on order and approvals.
3. Get it priced before it is built
Ask for the cost and the effect on the programme, in writing, before the work goes ahead. Leaving work out can reduce the price. A change that waits for a new drawing or a special order can hold up the trades that follow.
Under a fixed quote, the trader cannot charge more than quoted unless you ask for extra work, they tell you it is needed and you agree to pay more, or the quoted price was a genuine mistake[6][7]. Where a contract fixes no price for a service and does not say how one is fixed, the Consumer Rights Act 2015 says you pay a reasonable price, and no more[8]. Agreeing the price first avoids arguing about what is reasonable.
4. Check whether it needs fresh approval
If the change alters something the council or a neighbour has agreed, that approval may need updating before the part is built. The routes are set out below.
5. Confirm the decision in writing
Confirm it from both sides, signed or by email. Give the change a number, a description, the price or how it will be worked out, the programme effect, who asked for it and the drawing revision. Record rejected changes too.
6. Build it and update the log
Only then should the work go ahead. Add the change to the log and file the revised drawing with any approval. The running total shows where the final account is heading.
Provisional sums: when an allowance becomes a firm price
A provisional sum is money set aside for work that cannot yet be fully described and measured[9]. RICS separates defined provisional sums, where the nature, fixing and extent of the work are known, from undefined ones, where they are not[9].
Examples are timber repairs hidden under a floor, or a drain connection that depends on what is found. Once the work opens up, the allowance is replaced with a firm price. Treat that like any other change: get the price in writing first and record the difference, up or down.
Which changes need a fresh approval?
Three separate approvals can be affected. The table sums them up, and the notes below add the detail.
When a change needs a fresh approval
| Approval | When a change can affect it | Route | Who decides | Fee and timing |
|---|---|---|---|---|
| Planning: minor change | A small change to the approved drawings, such as a window moved or a material swapped | Non-material amendment under section 96A[1] | The council, which must be satisfied the change is non-material[1] | £46 householder fee from 1 April 2026[11]; decision within 28 days of a valid application[1] |
| Planning: larger change | A change too big to be non-material that keeps the same description of development | Minor material amendment, made as a section 73 application[3] | The council; the result is a new permission[2] | £89 householder fee from 1 April 2026[11] |
| Planning: new scheme | A change the council does not accept as minor, or one that changes what the development is | New planning application[1][2] | The council | Fee and timescale of a new application |
| Building Regulations | A change to the design or materials in a full plans approval | Amended plans or details; a new application may be needed if the change is substantial[4] | The building control body | Send before that part is built |
| Party wall | A change to work described in a party wall notice or award, such as a beam bearing or a foundation | Check it against the notice or award, which describe the work[5]; raise it with the neighbour, or the surveyors, before it is built | The adjoining owner or the surveyors | Before that part of the work starts |
Scroll sideways to see all columns
Planning. A non-material amendment approves a minor change to a planning permission[1]. There is no statutory definition of non-material, because a change that is minor on one scheme can be material on another[2]. A minor material amendment goes in as a section 73 application, with a schedule of the changes and the reasons[3]. It creates a new permission, but it cannot change the description of the development[2].
Building Regulations. Where the job has full plans approval, expect building control to keep inspecting but ask for amended plans or details. A substantial change may need a new application[4].
Party walls. The notice describes the proposed work in full, and an award sets out what will be done, when and how[5]. A change to notifiable work, such as moving a beam bearing or deepening a foundation near the neighbour, should be raised before it is built.
Keeping a change log
A change log is one running list of every change, open or closed. A shared spreadsheet or a numbered email thread will do, as long as both sides keep the same one. For each change, record:
- a number and the date it was raised
- who raised it, and why
- a description, with the drawing or photo
- the price, or how it will be priced
- the effect on the programme
- any approval needed, and its status
- the decision, its date and who agreed it
Keep paperwork and photos and note dates as you go; if a problem arises, that is your evidence[7]. At the end, the log shows what was built differently from the drawings. That makes it the starting point for recording the final handover.
How E&N Build Group handles a change
On an E&N Build Group job, anything that departs from the written scope is agreed with you before it is built. The quotation you accept sets out how changes are priced, so a change is costed against it rather than invented on the day.
If you disagree about a change
These steps follow general consumer guidance and are not advice on your contract.
Check what was agreed. A quote is a promise to do the work at an agreed price; an estimate is the trader's best guess[7]. Compare the charge with the quote, the scope and the change log.
Look at why it changed. Where an estimate was exceeded, the final price should be reasonable, allowing for the changes and anything beyond the trader's control, such as materials costs rising[7].
- Put it in writing. Keep it factual, give the change number and say what you think is fair.
Use a neutral route. Alternative dispute resolution is a way of settling disagreements without going to court[7]. Where the sums are large or the contract is unclear, take independent advice.
- Keep approvals separate. A price dispute does not change what the planning permission, building control or a party wall award requires.
What a well-managed change leaves you with
Each change has a number, a description, an agreed price and a known effect on the programme. Any approval it needed was in place before it was built. The drawings match the site, and the log goes into the handover file.
