Guide · New build houses

Building a new house: planning, Building Regulations, warranties and the process

A new house needs planning permission, with any pre-commencement conditions met before work starts, and Building Regulations approval, with inspections and a completion certificate at the end. Lenders generally expect a structural warranty or a professional consultant's certificate. Self-builders can be exempt from CIL if they claim before starting.

New two-storey house under construction with scaffolding, stacked timber and open drainage trenches in front (illustrative)
A new house under construction · illustrative Fig. 01

Building a new house takes three kinds of permission before and during the work: planning permission, which decides whether and what you can build; Building Regulations approval, which decides how it is built and checked; and the paperwork that lets the house be lived in, mortgaged and sold. This guide takes each in the order you meet them, then sets out the stages of the build. How these approvals fit with the rest of the system is set out in the approvals framework.

Planning permission: full or outline?

Government guidance says there are two main types of application. Outline planning permission allows a decision on the general principles of how a site can be developed, granted subject to conditions requiring the later approval of one or more reserved matters[1]: access, appearance, landscaping, layout and scale[1]. A full application deals with everything at once.

  • Full permission. In England, development must begin within three years of the date permission is granted, unless the council directs otherwise[2].

  • Outline permission. The reserved matters must be applied for within three years of the outline grant, and the development must begin within two years of the final approval of the reserved matters[3].

  • What counts as beginning. Development begins with the first material operation, which includes any work of construction, digging a trench for the foundations, or laying an underground main or pipe to the foundations[4].

Planning conditions

Most permissions come with conditions. A pre-commencement condition is one that must be complied with before any building or other operation begins, and in England a council can't impose one without the applicant's written agreement to its terms, except in prescribed circumstances[5]. Government guidance says development carried out without complying with a pre-commencement condition would be unlawful and may be the subject of enforcement action[6].

Details required by conditions are submitted to the council in writing for approval, and the council charges a fee. It must give its decision within 8 weeks, or a longer period agreed in writing[6]. Build the time for this into the programme: groundworks can't start until the pre-commencement conditions are discharged.

Building Regulations approval

Before starting, you either give building control a building notice or apply for approval with full plans[7]. A full plans application is compulsory if the work is over or near a sewer covered by requirement H4, or if the house will front a private street[7]. GOV.UK says that with full plans you can expect a decision within 5 weeks, or 2 months with your consent, and that the building notice route is only for smaller projects and gives no formal approval[8]. You can use the council or a private registered building control approver[8].

  • Lapse. An approval lapses if the work isn't commenced within 3 years[9]. For a house, work is regarded as commenced when the sub-surface structure, including all foundations, any basement and the structure of the ground floor, is complete[10].

  • Notices during the build. You give notice before starting and wait at least two days, give a commencement notice within five days of work being regarded as commenced, and notify the stages building control chooses to inspect based on risk[11].

  • Completion. Within five days of completion you give a completion notice, including a statement signed by the client that, to the best of their knowledge, the work complies[11]. Building control then has eight weeks to issue a completion certificate, which is evidence, but not conclusive evidence, that the requirements have been met[12]. With a private registered building control approver, the work is covered by an initial notice and the approver gives a final certificate instead[37].

What a new house has to meet

  • Energy. The target and designed CO2 emission rates, with a list of specifications, must be notified to building control not later than the day before work starts[13], and an energy performance certificate given to the owner within five days of completion[14].

  • Water. Estimated water use must not exceed 125 litres per person per day, or 110 litres where the planning permission makes that a condition[15].

  • Overheating. New homes must limit unwanted solar gains in summer and provide an adequate means of removing heat, with mechanical cooling only where needed[16].

  • Electric vehicle charging. A new residential building with associated parking must have access to electric vehicle charge points[16].

  • Security and broadband. New dwellings must resist unauthorised access, and each must be connected to a gigabit-capable network, subject to exceptions[16].

The Future Homes Standard from 24 March 2027

New regulations implementing the Future Homes and Buildings Standards, with a new Approved Document L, come into force on 24 March 2027[17]. Government says the notional dwelling used to set the targets will include high fabric standards with enhanced airtightness, a high-efficiency air-source heat pump or a heat network connection, wastewater heat recovery for homes above one storey, and mechanical extract ventilation, and that the standard will effectively preclude fossil fuel heating systems[19]. A new house will normally also need a system for on-site renewable electricity generation on the building or within its curtilage, with limited exceptions[20], which government expects will usually be rooftop solar panels[19].

A house stays on the current rules only if a building notice or full plans application was given for it before 24 March 2027 and the work on it is commenced, meaning the foundations and ground floor structure are complete, before 24 March 2028[18]. Government says this applies building by building[17], so timing can change the specification and the cost.

Who is responsible for compliance?

Where more than one contractor is involved, the client must appoint a principal designer and a principal contractor in writing before the construction phase begins[21]. For a domestic client, someone having a home built not as part of a business, the client's duties to plan, manage and monitor for compliance are carried out by the contractor, or by the principal contractor, or by the principal designer if they agree this in writing; if a domestic client doesn't make the appointments, the designer and the contractor in control of each phase take on the roles[21]. HSE says a domestic client's construction safety duties under CDM 2015 normally pass to the contractor or principal contractor in the same way[22].

Who designs the house, and how the drawings, the engineer and the builder fit together, is covered in building from your drawings.

Structural warranties and lenders

UK Finance says lenders will generally only lend on a newly built, converted or renovated property where it is covered by a warranty scheme or a Professional Consultant's Certificate, and that the full new-build requirements are in section 6.7 of its Lenders' Handbook for England and Wales[23]. If you, or anyone who buys the house from you, will need a mortgage, check with the lender or conveyancer what they will accept and arrange it before work starts: UK Finance says the consultant giving a Professional Consultant's Certificate confirms they have visited the property during construction[23].

The Building Safety Act 2022 contains a duty on developers to provide a new build home warranty to buyers, but at the time of checking it had been brought into force only for limited purposes[24]. Separately, anyone who takes on work for or in connection with providing a dwelling owes a duty to see that it is done in a workmanlike or professional manner, with proper materials, so that the dwelling is fit for habitation[25], and a claim under that duty can be brought within 15 years[26].

CIL and the self-build exemption

The Community Infrastructure Levy only applies where the council has a charging schedule[29], and the exemption for developments under 100 square metres doesn't apply to a new dwelling[36], so a new house can be liable whatever its size. Self-build housing, a dwelling built or commissioned by someone who then occupies it as their sole or main residence, can be exempt[27], but the claim must be received by the council before the development commences[28].

  1. Assume liability for the levy (Form 2)[29].

  2. Submit the self-build exemption claim (Form 7 Part 1) and get the exemption before starting[29].

  3. Submit a commencement notice (Form 6), which must be received before work starts on site[29].

  4. Within six months of the compliance certificate, submit Form 7 Part 2 with the supporting evidence[29].

Government guidance says you must own the house and live in it as your principal residence for at least three years after the work is completed, or the levy becomes payable[29]. Councils also keep registers of people seeking plots for self-build and custom housebuilding[30].

Other things a new house needs

  • Drainage. You are entitled to connect your drains to the public sewer, but must give the sewerage company notice, and it has 21 days to refuse on specified grounds[31].

  • Water. The water company must make a connection to its main when the owner of premises where a building is proposed serves notice requiring a domestic supply[32].

  • An address. Councils give new buildings their official address through street naming and numbering[34].

  • Biodiversity net gain. For planning applications made on or after 6 August 2026, the self-build exemption no longer applies; sites of 0.2 hectares or below are exempt unless the development affects on-site priority habitat[33].

The stages of building a new house

The order of work is broadly the same on every house. The inspection stages are set by each building control body under the regulations[11]; Merton's building control, for example, lists commencement, excavation for foundations, oversite, new walls with below-ground drains and damp-proof course, ground floor insulation, wall and roof insulation and floor structure, drainage tests, and completion before occupation[35].

  1. Before work. Planning permission, pre-commencement conditions discharged, Building Regulations approval or notice, warranty and CIL arranged.
  2. Groundworks. Site set-up, foundations and below-ground drainage, inspected as they go.
  3. Up to ground floor. Oversite, damp-proof course and the ground floor structure, which is when the work counts as commenced for Building Regulations[10].

  4. Superstructure. Walls or frame, floors and roof, then windows and doors to make it weathertight.
  5. First fix and insulation. Electrics, plumbing and heating, insulation and plastering.
  6. Second fix and finishes. Kitchen, bathrooms, flooring and decoration.
  7. Completion. Completion notice, completion certificate, energy performance certificate and the handover documents[11][12][14].

Next steps

The site visit and the written quotation are free, and neither commits you to anything. Send the planning decision notice, the drawings and any structural calculations if you have them; if you don't yet, the design, structural engineering and submissions can be arranged. For how a new build is scoped and run, see our new build service.

FAQ

Questions people ask before building a new house.

Do I need planning permission to build a house?

Yes. A new house needs planning permission, either full permission or outline permission followed by approval of the reserved matters: access, appearance, landscaping, layout and scale. The permission usually comes with conditions, some of which must be met before work starts.

How long does planning permission last?

In England, development must normally begin within three years of the permission being granted, unless the council sets a different period. With outline permission, the reserved matters must be applied for within three years, and work must begin within two years of the final approval of the reserved matters.

What is a pre-commencement condition?

A condition that must be complied with before any building or other operation begins. In England, a council can't impose one without the applicant's written agreement, except in prescribed circumstances. Government guidance says development carried out without complying with a pre-commencement condition would be unlawful and may face enforcement action.

Do I need a structural warranty to build a house?

UK Finance says lenders will generally only lend on a newly built property where it is covered by a warranty scheme or a Professional Consultant's Certificate, so if you or a future buyer will need a mortgage, arrange one before work starts. Check with your lender or conveyancer what they will accept.

What is the Future Homes Standard and when does it apply?

It is the new energy standard for new homes, brought in by regulations that come into force on 24 March 2027. Government says it will effectively rule out fossil fuel heating, and most new homes will need on-site renewable electricity, usually solar panels. A house can stay on the current rules only if its building notice or application went in before 24 March 2027 and its foundations and ground floor structure are complete before 24 March 2028.

How do I claim the CIL self-build exemption?

Assume liability, then submit the self-build exemption claim (Form 7 Part 1) and a commencement notice (Form 6) before work starts, and the second part of the claim (Form 7 Part 2) with evidence within six months of the compliance certificate. You must then live in the house as your main residence for at least three years.

Can I use a building notice for a new house?

The regulations allow a building notice in some cases, but a full plans application is compulsory where the work is over or near a sewer covered by requirement H4, or where the house fronts a private street. GOV.UK describes the building notice route as only for smaller projects, without formal approval.

Does building one house need biodiversity net gain?

It depends on the site and when the application was made. For applications made on or after 6 August 2026, the self-build exemption no longer applies, but sites of 0.2 hectares or less are exempt unless the development affects on-site priority habitat. Where net gain applies, the development must deliver at least a 10% gain.

Sources

Where the rules above come from.

Official sources checked on 4 October 2026. Fees and permitted development limits change; the dates show when each was read.

  1. GOV.UK (MHCLG),
    Planning practice guidance: making an application
    (accessed 4 Oct 2026)
  2. legislation.gov.uk,
    Town and Country Planning Act 1990, section 91: general condition limiting duration of planning permission
    (accessed 4 Oct 2026)
  3. legislation.gov.uk,
    Town and Country Planning Act 1990, section 92: outline planning permission
    (accessed 4 Oct 2026)
  4. legislation.gov.uk,
    Town and Country Planning Act 1990, section 56: time when development begun
    (accessed 4 Oct 2026)
  5. legislation.gov.uk,
    Town and Country Planning Act 1990, section 100ZA: restrictions on power to impose planning conditions in England
    (accessed 4 Oct 2026)
  6. GOV.UK (MHCLG),
    Planning practice guidance: use of planning conditions
    (accessed 4 Oct 2026)
  7. legislation.gov.uk,
    The Building Regulations 2010, regulation 12: giving a building notice or applying for approval
    (accessed 4 Oct 2026)
  8. GOV.UK,
    Building regulations approval: how to apply
    (accessed 4 Oct 2026)
  9. legislation.gov.uk,
    Building Act 1984, section 32: lapse of approval
    (accessed 4 Oct 2026)
  10. legislation.gov.uk,
    The Building Regulations 2010, regulation 46A: when work is regarded as commenced
    (accessed 4 Oct 2026)
  11. legislation.gov.uk,
    The Building Regulations 2010, regulation 16: notices to the local authority
    (accessed 4 Oct 2026)
  12. legislation.gov.uk,
    The Building Regulations 2010, regulation 17: completion certificates
    (accessed 4 Oct 2026)
  13. legislation.gov.uk,
    The Building Regulations 2010, regulation 27: CO2 emission rate calculations
    (accessed 4 Oct 2026)
  14. legislation.gov.uk,
    The Energy Performance of Buildings (England and Wales) Regulations 2012, regulation 7A: energy performance certificates on construction
    (accessed 4 Oct 2026)
  15. legislation.gov.uk,
    The Building Regulations 2010, regulation 36: water efficiency of new dwellings
    (accessed 4 Oct 2026)
  16. legislation.gov.uk,
    The Building Regulations 2010, Schedule 1: requirements
    (accessed 4 Oct 2026)
  17. GOV.UK (MHCLG),
    The Future Homes and Buildings Standards: Building Circular 01/2026
    (accessed 4 Oct 2026)
  18. legislation.gov.uk,
    The Building Regulations etc. (Amendment) (England) Regulations 2026 (SI 2026/335), regulation 5: transitional provisions
    (accessed 4 Oct 2026)
  19. legislation.gov.uk,
    Explanatory Memorandum to the Building Regulations etc. (Amendment) (England) Regulations 2026
    (accessed 4 Oct 2026)
  20. GOV.UK (MHCLG),
    Approved Document L, Volume 1: Dwellings (2026 edition, in effect from 24 March 2027)
    (accessed 4 Oct 2026)
  21. legislation.gov.uk,
    The Building Regulations 2010, Part 2A: dutyholders and competence
    (accessed 4 Oct 2026)
  22. HSE,
    Domestic clients: roles and responsibilities
    (accessed 4 Oct 2026)
  23. UK Finance,
    Mortgage Lenders' Handbook: Professional Consultant's Certificate
    (accessed 4 Oct 2026)
  24. legislation.gov.uk,
    Building Safety Act 2022, section 144: new build home warranties
    (accessed 4 Oct 2026)
  25. legislation.gov.uk,
    Defective Premises Act 1972, section 1: duty to build dwellings properly
    (accessed 4 Oct 2026)
  26. legislation.gov.uk,
    Limitation Act 1980, section 4B: limitation periods for claims under the Defective Premises Act
    (accessed 4 Oct 2026)
  27. legislation.gov.uk,
    The Community Infrastructure Levy Regulations 2010, regulation 54A: exemption for self-build housing
    (accessed 4 Oct 2026)
  28. legislation.gov.uk,
    The Community Infrastructure Levy Regulations 2010, regulation 54B: procedure for the self-build exemption
    (accessed 4 Oct 2026)
  29. GOV.UK (MHCLG),
    Planning practice guidance: Community Infrastructure Levy
    (accessed 4 Oct 2026)
  30. legislation.gov.uk,
    Self-build and Custom Housebuilding Act 2015, section 1: registers
    (accessed 4 Oct 2026)
  31. legislation.gov.uk,
    Water Industry Act 1991, section 106: right to communicate with public sewers
    (accessed 4 Oct 2026)
  32. legislation.gov.uk,
    Water Industry Act 1991, section 45: duty to make connections with main
    (accessed 4 Oct 2026)
  33. GOV.UK (Defra),
    Biodiversity net gain: exempt developments
    (accessed 4 Oct 2026)
  34. GeoPlace,
    Street naming and numbering officer role
    (accessed 4 Oct 2026)
  35. London Borough of Merton,
    Building control: book an inspection
    (accessed 4 Oct 2026)
  36. legislation.gov.uk,
    The Community Infrastructure Levy Regulations 2010, regulation 42: exemption for minor development
    (accessed 4 Oct 2026)
  37. legislation.gov.uk,
    Building Act 1984, section 51: final certificates
    (accessed 4 Oct 2026)