Guide · New build houses

New build house costs and what affects them

The cost of building a house is set by the plot as much as the house: ground conditions and trees decide the foundations, and drainage and service connections vary from site to site. Then come the size, structure and specification, the fees and any levy. Building a new dwelling can be zero-rated for VAT, but professional fees are not.

Foundations and blockwork for a new house on a cleared plot, with heaps of soil and a mature tree beyond (illustrative)
Foundations on a new plot · illustrative Fig. 01

A new house is priced in two parts: what it costs to make the plot buildable, and what it costs to build the house on it. The first part varies the most and is the hardest to see before the ground has been investigated. This guide covers what drives the cost of building a new house, the fees and levies around it, VAT, and what a quote should include. It gives no price ranges, for the reason below.

Why there is no standard price

A cost per square metre assumes a level, accessible plot with good ground and a standard specification. Two houses of the same size can cost very different amounts if one needs deep foundations near trees, a long drainage run or a pumped connection, and the other doesn't. A reliable figure comes from a site investigation, approved drawings, a specification and a written scope.

What drives the cost of a new house?

The plot and the ground

The Building Regulations require a building to be constructed so that ground movement from swelling, shrinkage or freezing of the subsoil, or from land-slip or subsidence, won't impair its stability, and the ground under it to be cleared of material that might damage it, with reasonable precautions against contaminants[1]. Approved Document C says the preparation of the site will depend on the findings of the site investigation, which is also relevant to the foundations[2].

  • Clay and trees. Approved Document C says that where mature trees are present on sites with shrinkable clays, the potential damage from ground heave to services and floor slabs should be assessed, and rates London clay as having high to very high volume change potential[2]. Approved Document A sets minimum strip foundation depths of 0.75, 0.9 or 1.0 metres on low, medium or high shrinkage clay, which may need to be deeper where there are trees nearby[3]. The British Geological Survey says the rock formations most susceptible to shrink-swell behaviour are found mainly in south-east Britain[4].

  • Protected trees. Cutting the roots of a tree protected by a Tree Preservation Order needs the council's consent[5].

  • Contamination. If contaminants are found that the planning process didn't identify, Approved Document C says the council's Environmental Health department should be informed[2], and the work to deal with them is a cost of its own.

Size, shape and structure

A larger house costs more, but so does a complicated one: corners, bays, dormers, roof shapes and openings all add work compared with a simple form of the same floor area. The structure, whether masonry, timber frame or another system, affects the programme, the foundations and the trades involved. These are design decisions, best settled in the drawings before the house is priced.

Specification and the Future Homes Standard

Windows, heating, kitchens, bathrooms and finishes are where the specification shows, and choices here can move the price as much as the structure. From 24 March 2027, the energy standard for new homes changes. Government says the notional home used to set the targets will include high fabric standards, a high-efficiency air-source heat pump or a heat network connection, wastewater heat recovery for homes above one storey and mechanical extract ventilation, and that the standard will effectively preclude fossil fuel heating[6]. A new house will normally also need on-site renewable electricity generation, with limited exceptions[7], which government expects will usually be rooftop solar panels[6]. Government's view is that installing low-carbon measures at the point of construction is cheaper and less disruptive than retrofitting them later[6].

Timing matters: a house stays on the current rules only if its building notice or full plans application was given before 24 March 2027 and its foundations and ground floor structure are complete before 24 March 2028[8].

Drainage and service connections

  • Water and sewer. Water and sewerage companies in England set their new connection charges under Ofwat's charging rules and must publish them, or how they are calculated, in a single charging arrangements document; infrastructure charges recover the cost of reinforcing the network[9]. You must give the sewerage company notice before connecting to a public sewer[10].

  • Electricity. Ofgem's consumer guidance says you contact the local distribution network operator, which must calculate the cost using its connection charging methodology, published on its website, and offer terms within three months once it has the information it needs[11].

  • Building requirements that need services. A new house with associated parking needs access to an electric vehicle charge point, and each new dwelling needs a connection to a gigabit-capable network, subject to exceptions[1].

Fees, levies and warranties

  • Design and engineering. Architect's or designer's fees, structural engineering, a site investigation and energy calculations.
  • Planning application. Councils charge fees set by national regulations[13]; the government has confirmed plans to change planning fees, including letting councils vary them within limits[14], so check the current fee with your council.

  • Building control. GOV.UK says councils base their fees on their costs, with the amount depending on the type of work, the inspections, the number of dwellings and the floor area, and that private registered building control approvers negotiate their fees directly with you[12].

  • Community Infrastructure Levy. Each charging authority sets its rates in a charging schedule, expressed per square metre, and in London the Mayor also charges a levy that the boroughs collect[15]. Self-build housing occupied by its builder as their main residence can be exempt[16], but only if the claim is received before work starts[17].

  • Biodiversity net gain. Where it applies, a development must deliver at least a 10% gain in biodiversity value[19]. For applications made on or after 6 August 2026, self-build is no longer exempt, but sites of 0.2 hectares or below are, unless the development affects on-site priority habitat[18].

  • Building Safety Levy. Charged from 1 October 2026, but only where the work is, or is part of a wider development that is, major residential development of at least 10 dwellings[20][25], so it normally doesn't apply to a single house.

  • Warranty. UK Finance says lenders will generally only lend on a newly built property covered by a warranty scheme or a Professional Consultant's Certificate[21], so the cost of one belongs in the budget.

New build cost drivers

Driver What it adds Source
Shrinkable clay and trees Deeper or engineered foundations, heave precautions Approved Documents A and C[3][2]
Contaminated ground Investigation and remediation Approved Document C[2]
Future Homes Standard Heat pump or heat network, solar, higher fabric standards Explanatory Memorandum; ADL 2026[6][7]
Water and sewer Connection and infrastructure charges Ofwat[9]
Electricity Connection charge from the network operator Ofgem[11]
CIL Levy per square metre, unless exempt Planning practice guidance[15]
Biodiversity net gain At least 10% gain where it applies Defra; TCPA 1990[18][19]

Scroll sideways to see all columns

What should a new build quote include?

  • The drawings, specification and structural design it is priced against, with their revision numbers.
  • The foundations assumed, and what happens if the site investigation or the excavation finds different ground.
  • Drainage and service connections: what the builder does, and what is paid to the utility companies.
  • Which fees, levies, warranty and insurances are included, and which are paid by you.
  • The energy standard the house is built to, and the heating and renewable systems included.
  • Provisional sums, the programme, and how changes are priced.

Setting several quotes side by side is covered in comparing building quotes. With an E&N Build Group quotation you get a written scope before work starts, stating what is included, what is not, and what is provisional.

How does VAT apply to a new house?

HMRC says the construction of a new building is normally standard-rated, but a supply can be zero-rated when you are involved in constructing a qualifying building, such as one designed as a dwelling[22]. The conditions include that the building is built from scratch: any existing building must be demolished to ground level, though a cellar, basement or the ground-level slab can be kept[22].

  • Professional fees. HMRC says the supply of architectural, surveying, consultancy and supervisory services is always standard-rated[22].

  • Early work. Site investigation or demolition carried out before planning permission for the qualifying building has been granted is standard-rated[22].

  • Self-builders. The DIY housebuilders' scheme lets you make one claim to reclaim VAT on eligible materials and services; for work completed on or after 5 December 2023, you must apply no more than 6 months after finishing[23], using the online service or form VAT431NB, with the building regulations completion certificate as evidence[24].

Next steps

The site visit and the written quotation are free, and neither commits you to anything. Send the planning decision, the drawings, any site investigation and the specification, or tell us how far it has been decided. For how a new build is scoped and run, see our new build service.

FAQ

Questions people ask before pricing a new house.

How much does it cost to build a house?

It depends on the plot, the ground and the foundations it needs, the size and shape of the house, the structure, the specification, the service connections and the fees, levies and warranty. No price ranges are given here. A figure you can rely on comes from a written quotation against approved drawings and a specification.

What does a new house cost per square metre?

There is no single figure. A rate per square metre leaves out the things that vary most between plots: the ground and foundations, access, drainage and connections, and the specification. Ask for a quotation against your drawings instead, with provisional sums shown separately.

Is VAT charged on building a new house?

A builder's services in the course of constructing a new building designed as a dwelling can be zero-rated, if HMRC's conditions are met. Architects', surveyors' and other professional services are always standard-rated, and so is site investigation or demolition carried out before planning permission is granted.

Can a self-builder reclaim VAT?

Yes, through the DIY housebuilders' scheme, which allows one claim for VAT on eligible building materials and services. For building work completed on or after 5 December 2023, the claim must be made no more than 6 months after finishing, with the completion certificate as evidence.

Do I pay CIL on a new house?

Possibly, if your council charges the Community Infrastructure Levy; rates are set in its charging schedule per square metre. Self-builders who will live in the house can be exempt, but the claim must be received before work starts.

Will the Future Homes Standard change the cost?

It changes the specification. For houses not covered by the transitional rules, the new standard from 24 March 2027 means low-carbon heating, on-site renewable electricity such as solar panels and higher fabric standards. Government says installing these at construction is cheaper and less disruptive than retrofitting them later.

Who charges for water, sewer and electricity connections?

The companies that own the networks. Water and sewerage companies publish their new connection charges under Ofwat's charging rules, and the local electricity distribution network operator calculates its charges using its published connection charging methodology.

Does a single new house have to pay the Building Safety Levy?

Normally not. The levy, charged from 1 October 2026, applies to major residential development of at least 10 dwellings, or work that is part of a wider development of that size.

Sources

Where the rules above come from.

Official sources checked on 4 October 2026. Fees and permitted development limits change; the dates show when each was read.

  1. legislation.gov.uk,
    The Building Regulations 2010, Schedule 1: requirements
    (accessed 4 Oct 2026)
  2. GOV.UK (HM Government),
    Approved Document C: Site preparation and resistance to contaminants and moisture (2004 edition incorporating 2010 and 2013 amendments)
    (accessed 4 Oct 2026)
  3. GOV.UK (HM Government),
    Approved Document A: Structure (2004 edition incorporating 2010 and 2013 amendments)
    (accessed 4 Oct 2026)
  4. British Geological Survey,
    Swelling and shrinking soils
    (accessed 4 Oct 2026)
  5. GOV.UK (MHCLG),
    Planning practice guidance: tree preservation orders and trees in conservation areas
    (accessed 4 Oct 2026)
  6. legislation.gov.uk,
    Explanatory Memorandum to the Building Regulations etc. (Amendment) (England) Regulations 2026
    (accessed 4 Oct 2026)
  7. GOV.UK (MHCLG),
    Approved Document L, Volume 1: Dwellings (2026 edition, in effect from 24 March 2027)
    (accessed 4 Oct 2026)
  8. legislation.gov.uk,
    The Building Regulations etc. (Amendment) (England) Regulations 2026 (SI 2026/335), regulation 5: transitional provisions
    (accessed 4 Oct 2026)
  9. Ofwat,
    Charging rules for new connection services (English undertakers), effective from April 2026
    (accessed 4 Oct 2026)
  10. legislation.gov.uk,
    Water Industry Act 1991, section 106: right to communicate with public sewers
    (accessed 4 Oct 2026)
  11. Ofgem,
    Get or alter a gas or electricity connection
    (accessed 4 Oct 2026)
  12. GOV.UK,
    Building regulations approval: how to apply
    (accessed 4 Oct 2026)
  13. GOV.UK (MHCLG),
    Planning practice guidance: fees for planning applications
    (accessed 4 Oct 2026)
  14. GOV.UK (MHCLG),
    Fees for planning applications: government response (July 2026)
    (accessed 4 Oct 2026)
  15. GOV.UK (MHCLG),
    Planning practice guidance: Community Infrastructure Levy
    (accessed 4 Oct 2026)
  16. legislation.gov.uk,
    The Community Infrastructure Levy Regulations 2010, regulation 54A: exemption for self-build housing
    (accessed 4 Oct 2026)
  17. legislation.gov.uk,
    The Community Infrastructure Levy Regulations 2010, regulation 54B: procedure for the self-build exemption
    (accessed 4 Oct 2026)
  18. GOV.UK (Defra),
    Biodiversity net gain: exempt developments
    (accessed 4 Oct 2026)
  19. legislation.gov.uk,
    Town and Country Planning Act 1990, Schedule 7A, paragraph 2: the biodiversity gain objective
    (accessed 4 Oct 2026)
  20. legislation.gov.uk,
    The Building Safety Levy (England) Regulations 2025, regulation 6: major residential development
    (accessed 4 Oct 2026)
  21. UK Finance,
    Mortgage Lenders' Handbook: Professional Consultant's Certificate
    (accessed 4 Oct 2026)
  22. HMRC,
    Buildings and construction (VAT Notice 708)
    (accessed 4 Oct 2026)
  23. GOV.UK,
    Reclaim VAT on a self build home
    (accessed 4 Oct 2026)
  24. HMRC,
    Claim a VAT refund for a new home or charity building if you're a DIY housebuilder
    (accessed 4 Oct 2026)
  25. legislation.gov.uk,
    The Building Safety Levy (England) Regulations 2025, regulation 15: chargeable building control applications
    (accessed 4 Oct 2026)