Closing a shop for a refit costs trade, and closing an office sends staff elsewhere. The alternative is to keep trading in part of the premises while the work goes on in another. That only works if the phasing is planned before the price is agreed, because it changes the order of work, the hours and the protection needed.
This guide is for the owner, tenant or manager of a shop or office. It covers zones, out-of-hours work, safety while open, the legal duties, approvals and sign-off. It does not cover the trades themselves. For new layouts, see partitions and ceilings for commercial units.
What to settle before the work is phased
Five questions shape the plan. Written down, the answers form the core of the project brief.
Who the client is. Under the Construction (Design and Management) Regulations 2015, known as CDM 2015, a commercial client is any person or organisation that carries out a construction project as part of a business[5]. That can be the tenant, the landlord or both.
- What the lease allows. If you lease the premises, read the alterations clause before the scope is fixed. Where it needs the landlord's consent, get it in writing before work starts. Landlords often give it as a formal licence for alterations.
Who is responsible for fire safety. In a workplace, the responsible person is the employer, to the extent the premises are under their control. A landlord and a tenant can both be responsible persons, and must then co-operate[2].
What is known about asbestos. The duty to manage asbestos applies to all non-domestic premises, such as shops. The dutyholder must tell anyone who may work on or disturb asbestos where it is and what condition it is in[3]. Ask for the asbestos register early.
- When the business can close. List the busiest hours, delivery times and any days the premises could close entirely.
How to phase the works, step by step
1. Divide the premises into zones
Mark on a plan what must keep working: the entrance, tills or reception, toilets, kitchens, the comms room and every escape route. The rest becomes zones that close in turn. Each zone needs its own way in for workers and materials, away from customers where the layout allows.
2. Put the zones in trade order
Within each zone, structural work comes first, then services such as electrics and plumbing, then finishes. Services often cross zone boundaries, so a new distribution board may need a shutdown that affects the whole premises. Plan it for a closed day. E&N Build Group carries out work in that order, and anything that departs from the written scope is agreed with you before it is built.
3. Decide what moves outside trading hours
Some work can be done in the evening, overnight or at weekends, while the premises are closed. It suits short, disruptive tasks, such as a services shutdown or a floor across an entrance. Not every contractor offers it, and it can change the price, so ask at the quotation stage.
Noisy work has its own limits, set by the council. Croydon Council, for example, sets hours for noisy work of 8am to 6pm on weekdays and 8am to 1pm on Saturdays, with none on Sundays or bank holidays. Contractors must show an overriding reason for noisy work at night, and being behind schedule does not count[11]. Quiet fitting and finishing suits the evening; breaking out does not.
4. Separate the work area from the open area
HSE guidance is that construction work must not put members of the public at risk. The site boundary should be defined physically where necessary, and unauthorised people kept out[6]. Inside a shop or office, that means a solid screen between the zone and the trading area, a door kept shut, and signs. Seal dust screens at the edges and protect the floors on the materials route.
5. Keep escape routes and fire precautions working
Escape routes must be kept clear at all times, and exit doors must open easily in an emergency without a key or code[1]. Check every screen, skip and pallet against the escape plan at the end of each shift. Fire safety controls should be placed on contractors working on the premises, which can include hot work permits[1]. If a phase closes an exit or moves a route, agree it with the responsible person first.
6. Hand back each zone before the next one closes
Finish, clean and inspect each zone before it reopens, and walk the escape routes with the responsible person. Then close the next zone. The table shows how this can look on premises that stay open.
Example phasing for premises that keep trading
| Phase | What stays open | Controls |
|---|---|---|
| Before work starts | The whole premises | Asbestos survey in a vacated area[4]; approvals and landlord's consent in place; CDM arrangements made[5]; fire risk assessment reviewed for the works[2] |
| Phase 1: back of house (stockroom, staff areas, plant) | Sales floor or office floor, tills or reception, customer toilets | Screened zone with its own access; escape routes kept clear[1]; services shutdowns on a closed day |
| Phase 2: first half of the front area | The other half, with a marked temporary route | Solid screens, signs, unauthorised people kept out[6]; noisy work within council hours[11] |
| Phase 3: second half of the front area | The finished first half | As phase 2; the first half inspected and handed back before this phase starts |
| Shopfront and signs | The interior, through a protected entrance | Planning permission[9] and advertisement consent where needed[10]; nothing able to fall outside the site boundary[6] |
| Completion | The whole premises | Completion certificate[8]; electrical certificate[13]; fire risk assessment reviewed for the new layout[2] |
Scroll sideways to see all columns
What the business must do while the works go on
The Regulatory Reform (Fire Safety) Order 2005 applies to virtually all premises other than single private homes[2]. The responsible person must carry out a suitable and sufficient fire risk assessment, record it and keep it under regular review[1]. A review is needed after a significant relevant change[2], and a phased refurbishment can be one at each phase. The local fire and rescue service normally enforces the law[1].
Before any structural work begins, a refurbishment and demolition survey must locate and identify asbestos, including materials hidden in the building fabric. The survey is destructive, so the area must be vacated while it is done. The surveyor then confirms it fit to reoccupy, and HSE strongly recommends an accredited surveying organisation[4]. For a business that stays open, that means surveying zone by zone, or while closed. Asbestos must be removed, as far as reasonably practicable, before major refurbishment[4].
CDM 2015 places duties on commercial clients on every project, whatever its size. The client makes suitable arrangements for managing the project, with enough time for each stage. The client provides pre-construction information, makes sure welfare facilities are provided, and appoints a principal designer and principal contractor where there is more than one contractor[5].
Larger projects must also be notified to HSE. A project is notifiable where the work will last longer than 30 working days and involve more than 20 workers at any one time, or will exceed 500 individual worker days. The client notifies HSE, and a copy is displayed in the site office[5].
Which approvals might the work need?
Building Regulations apply to building work, which includes the material alteration of a building and the provision or extension of a controlled service or fitting[7]. Ask the designer which parts of the scope count. Where the Fire Safety Order applies, as it does to shops and offices, a council application must use full plans, not a building notice. The council consults the fire authority and must decide within five weeks, or two months if you agree[8].
You will probably need planning permission to make a major change to a building or to change its use[9]. A new shopfront changes the outside of the building, so ask the council's planning team before it is designed. All advertisements need consent, either express or deemed. Many traditional fascia and hanging signs that are not lit are likely to have deemed consent, subject to conditions such as size. Displaying an advert without consent is a criminal offence[10].
The landlord's consent under the lease is a separate approval. None of these replaces another.
Common problems when the premises stay open
Suspected asbestos is found mid-phase. Stop work in that area and keep it closed. The survey before work starts exists to find hidden materials[4], and the dutyholder keeps the register up to date[3].
Noisy work cannot be done at night. Council rules may not allow it[11]. Move it to a closed day, or close the next zone for the hours it takes.
- Dust reaches the trading area. Check the screen seals and the door between zones, then the materials route.
An escape route gets blocked. Clear it at once: escape routes must be kept clear at all times[1].
- A services shutdown overruns. Start shutdowns at the beginning of a closed period, not the end, to leave time to restore power or water.
What you should have at sign-off
Collect these before the last zone reopens.
Building Regulations completion certificate. Ask for it when the application is made; the council issues it once it is content that the work complies[8].
Electrical certificates. Part P covers electrical work only in homes. In commercial buildings the Electricity at Work Regulations 1989 apply, and all electrical work should follow BS 7671[12]. Ask for the certificate for the work, such as an Electrical Installation Certificate[13].
A reviewed fire risk assessment for the new layout, with a record kept[1][2].
An updated asbestos register showing anything found or removed[3].
The health and safety file, where there was a principal designer[5].
At handover you receive the certificates and sign-offs that apply to the work done.
Next steps
Commercial work is one of the services E&N Build Group offers, and our commercial works service sets out the trades involved. The site visit and the written quotation are free, and neither commits you to anything. With the quotation, you get a written scope stating what is included, what is not, and what is provisional because it cannot be known until the work opens up. Design and Building Control submissions can be arranged through us, or we can build from your own designer's drawings.