Guide · Flooring

Subfloor preparation before tile or wood flooring

Before tile or wood flooring goes down, the subfloor must be sound, dry enough and flat enough for the product being laid. The doors, kitchen units, skirting and any underfloor heating also need a plan. This guide covers how each is checked, where the published figures come from, and who lifts the old floor.

Bare screed subfloor prepared for new flooring (illustrative)
Subfloor ready · illustrative Fig. 01

A new tiled or wood floor is only as stable as the base under it. That base has to be identified, checked and prepared before anything is laid, and the edges matter as much as the middle.

This guide sets out the checks in order, the published drying and flatness guidance, and who lifts the old floor. It does not cover choosing a floor or diagnosing one that has failed. Both floor types are part of our flooring services, and each can be booked as a standalone job.

What to have ready before the floor is checked

Settle these first, because the checks depend on what is going down:

  • The floor you want. Tile or wood, and the type: porcelain, ceramic or stone; engineered or solid boards.
  • The product's instructions. The adhesive, boards, underlay and any membrane each have a data sheet or installation instructions. The Tiling Guide refers to the maker's data sheets and recommendations at several steps[2]. They set the moisture, flatness and fixing details.

  • What is down now, and the building's age. Age matters for old vinyl and floor tiles, covered below.
  • Underfloor heating. Whether it is in or planned, and whether it is a water or an electric system.
  • Other work in the room. A new kitchen, new doors, skirting or plaster changes when the floor goes down.

How a subfloor is checked, step by step

1. Find out what the existing floor is

The common bases are a sand and cement screed, a calcium sulfate (anhydrite) screed, a concrete slab, timber boards on joists, and a chipboard deck. Many have an old covering on top. The base often shows only once that is lifted, so its condition stays provisional until then.

2. Check the condition and stiffness

Tiling guidance is that a base must be clean, dry and dimensionally stable, able to carry the tiling for the traffic it will get[2]. The checks differ by base:

  • Screeds and slabs. Cracks, hollow patches and old adhesive are noted. A calcium sulfate screed forms a weak surface layer, called laitance, which is abraded and vacuumed off before tiling[2].

  • Timber floors. Loose boards are refixed. A floor that bounces because a joist is damaged is a structural repair, assessed on site, not hidden under a thicker board.
  • Existing tiles or vinyl. A loose or cracked covering comes up. A sound one may be covered if the new product allows it, after the asbestos check below.

For tiles on timber, The Tile Association's FAQ gives 15 mm as the minimum plywood overlay recommended in BS 5385-3. It is screwed to the joists without damaging pipes or cables below[1]. Its 2026 Tiling Guide says plywood and other wood-based boards should not be used for direct tiling[2]. Chipboard is a wood-based board too. So the build-up over timber comes from the tile and adhesive makers' system, and is written into the floor tiling scope.

3. Check the moisture

A base must be dry before tiling[2]. The Tile Association gives these drying figures:

  • Sand and cement screed. Cure for at least 7 days, kept from drying too fast, for example under polythene. Then allow a further 2 weeks to dry[1].

  • Calcium sulfate screed. Allow 1 day per mm up to 40 mm, then 2 days per mm, in a ventilated room at 20°C or more. The target is no more than 1% moisture by weight, or 75% relative humidity[2]. On that rule, a 50 mm screed needs about 60 days.

These figures are for tiling under set conditions, and a reading is still taken before laying. For a concrete slab, the adhesive or flooring maker sets the limit and the test. For wood, the board's instructions set the subfloor moisture limit, the test, any damp-proof membrane and any time the boards need in the room. The wood flooring scope should name the board, so those instructions are known before a date is fixed.

4. Check levels and flatness

A base must be suitably level for the fixing method intended[2]. For floor tiling, the guidance is to check the overall flatness and use a levelling compound if required. Ready-mixed adhesives usually have a maximum bed depth of 3 mm and are not suitable for floors. Some surfaces need priming, and the data sheet says which[2]. Wood boards and their underlay have their own flatness limits.

Each layer adds height, from levelling compound to the finished floor. Add them up early: the total decides what happens at the doors and the kitchen units.

5. Plan the edges and interfaces

  • Doors. A higher floor can mean trimming doors and fitting a threshold strip to the next room. Check how any step will sit at outside doors.
  • Kitchen units. The floor goes in before the units or up to the plinths afterwards. Decide at layout stage, because it changes unit heights and whether appliances slide out.
  • Skirting. It either comes off and goes back over the floor, or stays with a beading. Any expansion gap the board's instructions require is hidden there.
  • Water underfloor heating. For tiles, it should be fully commissioned in controlled stages, before and after tiling, following the maker's guidance on drying times, adhesives and grouts[2]. Under wood, follow the board's instructions.

  • Electric underfloor heating. A new circuit is notifiable, and so is altering a circuit in the space around a bath or shower. Notifiable work is self-certified by an installer registered with a competent person scheme. Otherwise it is inspected, approved and certificated by a building control body or, in England, a third-party certification scheme electrician, who must be notified before work starts[5].

6. Agree who prepares and removes what

Preparation and laying can fall to different people. Agree in writing who handles:

  • Lifting and disposing of the old covering, gripper and underlay.
  • Moving furniture and appliances out and back.
  • Removing and refitting skirting, doors, plinths and any radiators in the way.
  • Base repairs: refixing boards, filling, levelling, priming, overlays or membranes.
  • Moisture readings: who takes them, and against which limit.
  • Commissioning underfloor heating, and connecting and certifying an electric system.

Before work starts you get a written scope with the quotation. It states what is included, what is not, and what is provisional because it cannot be known until the old floor is up.

Old vinyl and floor tiles: check for asbestos first

Asbestos may be part of any home built or refurbished before 2000[3]. HSE lists PVC and thermoplastic floor tiles, sheet coverings and screeds among the floor materials it was added to. Some were stuck down with mastics containing it, and old tiles can be hidden under carpet. They can be hard to identify[4].

Do not lift, scrape, sand or grind it yourself

HSE advises against repairing or removing asbestos materials yourself without training for non-licensed asbestos work. Materials assessed as in good condition and unlikely to be damaged should be left in place and monitored[3]. Grinding off flooring materials needs an HSE licensed contractor, and anyone who thinks they have found asbestos must stop work[4]. Analysts for asbestos work must be accredited by UKAS[3]. Their result decides whether the old floor is covered or removed, and by whom.

What each type of base needs

Where the table says the product sets the limit, the figure comes from the chosen adhesive, board or membrane.

Subfloor checks by type of base

Existing floor What gets checked Published guidance and where limits come from
New sand and cement screed Curing, drying, surface strength, flatness Cure at least 7 days, protected, then dry a further 2 weeks before tiling[1]; for wood, the board's instructions
New calcium sulfate screed Drying, moisture reading, surface laitance 1 day per mm up to 40 mm, 2 days per mm beyond, to no more than 1% by weight or 75% RH; laitance removed[2]
Concrete slab Dryness, flatness, old adhesive or paint Clean, dry and level for the fixing method[2]; moisture limit from the product's maker
Suspended timber floor Loose boards, bounce, damaged timber, services below Plywood overlay at least 15 mm under BS 5385-3[1]; wood-based boards not for direct tiling[2]
Chipboard deck Movement, moisture damage, fixings Wood-based board, not for direct tiling[2]; for wood, the board's instructions
Existing tiles Bond, cracks, hollow areas, added height Clean and stable; priming may be needed[2]; the new product's instructions decide
Old vinyl or thermoplastic tiles Age of the building, possible asbestos May contain asbestos if pre-2000[3][4]; not disturbed until identified

Scroll sideways to see all columns

What can turn up when the old floor comes up

  • Hollow or loose screed. The base must be stable[2], so it is repaired before laying.

  • A damp reading. More drying time, or a membrane the product's maker approves. A leak is fixed first.
  • A floor well out of level. Levelling raises the floor, so doors may need trimming. A large fall is looked at before it is levelled over.
  • Old adhesive or paint. The base must be clean[2], so residues are removed or primed as the data sheet directs.

  • Possible asbestos. Work on that covering stops until it is identified[4].

Anything that departs from the scope is agreed with you before it is built.

What a ready subfloor looks like

At the end of preparation, the base is clean, sound and stable, dry to the product's limit and flat enough for the fixing method. The finished height is known, and the doors, skirting, plinths and heating each have an agreed plan. The floor then goes down, with whatever curing time the adhesive and grout instructions set. At handover you receive the certificates and sign-offs that apply to the work done. Looking after the floor is covered in caring for the installed floor.

FAQ

Questions people ask before a new floor goes down.

What should be checked before a new wood floor is laid?

Four things. What the subfloor is, and whether it is sound and stable. Whether it is dry enough, measured against the limit in the board's installation instructions. Whether it is flat enough for the board and its underlay. And how the new floor will meet the doors, skirting, kitchen units and any underfloor heating. The board's instructions also say whether the boards need time in the room before they are laid.

How do you prepare a floor for tiling?

The Tile Association's rule is that the base must be clean, dry, stable and level enough for the fixing method. Getting there can mean lifting the old covering, refixing loose boards, adding an overlay on a timber floor, removing the weak surface layer from a calcium sulfate screed, levelling and priming. The adhesive maker's data sheet sets the details. Underfloor heating is commissioned in stages, before and after tiling.

How long should a new screed dry before tiling?

It depends on the screed. The Tile Association says a cement-based screed should cure for at least 7 days, protected from drying too fast, then dry for a further 2 weeks. A calcium sulfate screed needs 1 day per mm up to 40 mm and 2 days per mm beyond that, in warm, ventilated rooms. Its target is no more than 75% relative humidity. A reading is taken before laying.

Can you tile straight onto floorboards?

Not directly. Tiles need a stiff, stable base, and timber moves as its moisture content changes. The Tile Association's FAQ cites BS 5385-3 for a plywood overlay at least 15 mm thick. Its 2026 Tiling Guide says plywood and other wood-based boards should not be used for direct tiling. So the build-up over a timber floor follows the tile and adhesive makers' system, after loose or damaged boards are dealt with.

Can new flooring go over old tiles or vinyl?

Sometimes. The old covering must be sound, well bonded, clean and stable, and the extra height has to work at the doors and kitchen units. The new product's instructions decide whether it can be covered and what priming it needs. In a home built or refurbished before 2000, old vinyl or floor tiles may contain asbestos. They are not lifted, sanded or ground until they have been identified.

Does underfloor heating need to be commissioned before tiling?

Yes, for tiles. The Tile Association says underfloor heating should be fully commissioned in controlled stages, before and after tiling, to keep drying shrinkage down. The heating maker's guidance on drying times, screed thickness, adhesives and grouts should be followed. For wood over underfloor heating, the board's installation instructions set the conditions. An electric system is electrical work, and some of it is notifiable under the Building Regulations.

Who removes the old flooring?

Whoever the written scope names. Lifting and disposing of the old covering, moving furniture, taking off skirting and kitchen plinths, and repairing the base can each fall to the homeowner, the floor layer or the builder. Agree each item before work starts. The written scope that comes with the quotation states what is included, what is not, and what stays provisional until the old floor is up.

Sources

Where the rules above come from.

Official sources checked on 1 October 2026. Fees and permitted development limits change; the dates show when each was read.

  1. The Tile Association,
    Frequently asked questions (cement:sand screeds; plywood overlay on a timber floor)
    (accessed 1 Oct 2026)
  2. The Tile Association,
    The Tiling Guide (2026)
    (accessed 1 Oct 2026)
  3. HSE,
    Asbestos: FAQs
    (accessed 1 Oct 2026)
  4. HSE,
    Locations of asbestos and taking the right action
    (accessed 1 Oct 2026)
  5. Planning Portal,
    Electrics: Building Regulations general information
    (accessed 1 Oct 2026)